Wet Pan Mill

Wet Pan Mill photo-1
Wet Pan Mill photo-2
Wet Pan Mill photo-3
Wet Pan Mill photo-4
Wet Pan Mill photo-5
US$ 4600 ≥5 Sets
Key Specifications
Get Latest Price
Type:
Other
Warranty:
6months
Motor Power:
7.5kw
Payment & Shipping
Payment Methods:
Port of Shipment:
QINGDAO
Delivery Detail:
10 days
Type Other
Warranty 6months
Motor Power 7.5kw
Condition New
Motor Type AC Motor
Rotationl Speed 13-15r/min
Application Mine
Materials Iron
Transport Package NO
Specification QS-120
Trademark QIANSHENG
Origin CHINA

Wet pan mill instructions

 

1、foundation treatment

Prepared with cement, stone, mortar in proportion to stir well, horizontal surface to deal with 30 cm thick, solidification in 7 to 10 days before being installed.

2, the installation of equipment

(1) frame according to the level of installed, the basin set on the rack, the school good center, and then put the basin below four fixed bolt lock on the rack.

(2) in birdbath uniform party put gravel, 3-5 cm, and then put a good run on the top of the sand bottom, and adjusted the center in four directions. (bottom that comes out to mill large axial distance is less than 1 cm) at every point

(3) rod rolling mill machine installation: establish the two rollers with lifting equipment on the ground, in the middle of the roller into the roller core, with bolt locking roller core and flange. To hang one of the first grinding roller in the correction good grinding groove, and connecting rod set into the big shaft, bolting roller core shaft, connection was complete crane another grinding roller in the grinding slot and connected to the link rod. Two roller connected to complete, pay attention to the connection rod running direction.

(4) the power supply is connected.

(5) empty machine try starting, adjust the roll and grinding groove around the gap, the roller is equidistant from ground on both sides of the groove shall prevail.

(6) empty machine turn 15 minutes to vibrated pan under the sand, each part of the check the bolt is loose.

The ground with cement concrete bottom not filled the gap between plate with water, and system cant do it, so that grinding ore smoothly into the groove in the middle and quickly crushed ore.

(3) the water in the cement mortar solidification period, can be turned on, add water, add mine, start production.

3, use and maintenance

1, the mill running before feeding.

2, belt is expected to start, for downtime starts again, must first put residual ore grinding groove in the middle of the clearing, and start again.

3, uniform loading, not more and less, it is best to use the feeder.

4, bearing part must often add lubricant, deceleration machine must always check whether the lack of machine oil.

5, often check whether each part bolt looseness.

6, such as bearing damage, it must be change in time, lest cause eccentric shaft damage to other components.

7, equipment operation, pay attention to the speed reducer and bearing part of the presence of abnormal sound, whether any temperature rise too high, abnormal phenomenon such as motor current is too large; If you have the above phenomenon, should immediately stop ruled out.

8, inspection machine, to ensure safety, must remove the motor belt.

4、technical parameters

 

type

Roller

diameter

Disk diameter

Max feed

Revolutions per minute

Power

(KW)

weight

Daily output

900

900

1585

16-18

    3

2.1

1.5-3T

110

1100

2060

14-16

5.5

4.2T

5-6T

120

1200

2080

15-16

7.5

4.7T

6-8T


Product Tags: wet pan mill , pan mill , double wheel dressing machine

Send Inquiry to This Supplier

* Message
0/5000

Want the best price? Post an RFQ now!
Verified Business License
Business Type
Manufacturer
Year Established
2019
Factory Size
3,000-5,000 square meters
Annual Export Value
US$2.5 Million - US$5 Million