Plastic Rectangle Lunch Box Mold
ENA mould is specializing in crate mould, pallet mould, paint bucket mould, food container mould, flower pot mould and garbage bin mould. For the detailed of the company information, please view our "company profile" on alibaba carefully. You will get a completed view of this company
Taizhou Mould Factory
Detailed description of the plastic rectangle lunch box
Basic mould information:
Runner Type |
YUDO Hot Runner |
Mould Size |
560*530*610mm |
Mould Weight |
350Kg |
No. of Cavity |
1 cavity |
Product capacity |
5L bucket |
Product Material |
pp |
Product Weight |
146g |
Wall thinkness |
0.8mm |
Surface finish |
High polish |
Delivery Time |
50 days |
There are three levels of mould quality for your option.
Option A: Level A quality (Highest Level Quality)
Mould Base: LKM, 45# Steel
Core/Cavity: S136+Becu
Slider/Insert: S136
Mould spare parts: SKD 61
Hot Runner: YUDO
Mould Life: 1,000,000 shots
Cycle Time: 28s
Option B: Level B quality (Middle Level Quality)
Mould Base: 45# Steel, self-made
Core/Cavity: 718H
Slider/Insert: 718H
Mould spare parts: China Brand
Hot Runner: China Brand
Mould Life: 800,000 shots
Cycle Time: 30s
Option C: Level C quality (Lowest Level Quality)
Mould Base: 45# Steel, self-made
Core/Cavity: P20
Slider/Insert: P20
Mould spare parts: China Brand
Hot Runner: China Brand
Mould Life: 5,000,000 shots
Cycle Time: 32s
Attention pls:
Price varies in different quality level. When you send us the mould inquiry, please offer the following information:
1) Quality level you choose: Level A/Level B/Level C
2) Paint bucket Photo
3) paint bucket capacity
4) paint bucket wall thickness
Plastic Mould tool Making Process
Processing |
Time |
Prepare Steel |
7days |
Surface Dealing |
3days |
Lathe, Crude Machining |
7days |
Drill |
4days |
Heat Treatment |
5days |
Lathe, Precision Machining |
8days |
Precision CNC |
5days |
Polish |
6days |
Assembling and Fitting |
3days |
T1 mould test |
2days |
Total: It is 50 days for first mould testing after mold design is confirmed.
Plastic Mould tool Quality Control
For the Q/C of mould, there are 3 steps:
1. Mould Material Q/C
- Mould Steel Checking (Hardness, flaw detection)
- Mould Standard Spare Parts Checking (hardness, size, flaw checking)
2. Mould Making Process Q/C
- design checking (part design, mould design, mould engineering drawing)
- Each part of mould’s size checking after machining according to 2D drawing
- mould testing (check mould running condition)
3. Check with customer’s requirement again before mould shipping.
Plastic Mould tool Pack and Shipping
Anti-rust oil is painted first, then Plastic film, and finally Wooden Case.



Send Inquiry to This Supplier
You May Also Like
-
Agriculture Using Plastic Shape Moulds Heart, Star, Square, Flower Shape for Cucumber, Watermelon, StrawberryNegotiableMOQ: 500 Pieces
-
Genyond Factory 300-1000kg/h Toilet & Laundry Production Line Processing Plant Soap Making Machine Price From OilNegotiableMOQ: 1
-
OEM Customized Molded Enclosure Injection Plastic Molding For ElectronicsNegotiableMOQ: 1
-
Brand New Waterproof Pvc Flooring With Great PriceUS$ 80 - 117MOQ: 1 Piece
-
Mould For ScrubberNegotiableMOQ: 1
-
6.35mm Adjustable M2-M10 Carbon Steel Body Die Holder Wrench Set for Power ToolsUS$ 1 - 30MOQ: 640 Pieces
-
2016 Hot Selling Concrete Plastic Paving Mould for Interlock Tile MakingUS$ 1 - 5MOQ: 500 Pieces
-
ABS Fan Parts Plastic Cover ProductsUS$ 0.1 - 5MOQ: 1000 Sets
-
Standard Square Aluminium Stamping Sheet Cnc Machining PartUS$ 5 - 10MOQ: 100 Pieces
-
New Technology Wall Panel Moulding MachineUS$ 1,000 - 50,000MOQ: 1 Set